PROJECT DETAILS

 

Amherst, MA

Created a Student Support Center with its own entrance to respond to a variety of needs, from counseling to nursing and guidance

Completed in July, 2026

— Budget

NEEC has 640-ton heating/cooling capacity; 70 wells at 800 ft depth each; TES has 2.3M gal thermal capacity

— SF

NEEC has the capacity to support an additional 40,000 square feet and the infrastructure is expandable with additional wells and related ground source heat pumps to accommodate additional buildings in the future

ARTICLES & REFERENCES

 
 
Next
Next

Amethyst Apartments